FCCU Olefins Project & Turnaround
Off-site fabrication included steelwork, pipework and associated supports. The on-site pre turnaround work included the installation of 140 ton steelwork, new exchangers, fin fans, pumps and filters into a live unit. The project scope concluded with 600 tie-ins during a 7 week turnaround.
Subcontractors Managed
Scaffolding, Painting, Insulation,
Craneage,
NDT, E&I, Vessel Cleaning, Standby’s,
Refractory,
Machining.
Peak Labour 323